White House Protest Corps


Safety issue at Calvert Cliffs could spur additional oversight

Safety issue at Calvert Cliffs could spur additional oversight

By Liz F. Kay, The Baltimore Sun

3:51 p.m. EDT , June 15, 2010

Federal regulators investigating an automatic plant shutdown in February of the Calvert Cliffs nuclear power plant have found a safety issue deemed of low to moderate significance that may spur additional oversight.

Both reactors at the Lusby plant, owned by Constellation Energy Nuclear Group, shut down after an electrical malfunction caused by melting snow on a leaky roof prompted first one then a second reactor to shut down, a company spokesman said at the time.

Inspectors for the U.S. Nuclear Regulatory Commission said they found some equipment at the plant had been used longer than the manufacturer recommended, without tests to determine whether it was still reliable, according to an NRC spokesman.

Dave Fitz, a spokesman for Constellation Energy Nuclear Group, said company officials were reviewing the findings.

“We’ve taken some immediate corrective actions and some long-term actions are planned,” he said.

NRC inspectors will finish its assessment within 90 days, and Constellation can either request a conference or provide additional information in writing. If the safety concern finding is finalized, then the NRC would provide additional oversight until the problems have been addressed.

The company has not yet determined whether to challenge the NRC’s findings, Fitz said.

http://www.nirs.org

Advertisements


Maryland: Brand-New Calvert Cliffs Nuke Plant ( unless activists can stop it )

New Nuke Plant on the way in Maryland!

Calvert Cliffs Nuke Power Plant

Calvert Cliffs Nuke Power Plant

Beyond Nuclear
6930 Carroll Avenue Suite 400
Takoma Park, MD 20912
Tel. 301 270 2209
www.beyondnuclear.org

http://en.wikipedia.org/wiki/Calvert_Cliffs_Nuclear_Power_Plant


Hoyer expects action on reactor

http://www.somdnews.com/stories/05282010/rectop140417_32178.shtml

Optimistic about loan guarantees at tele-town hall

Friday, May 28, 2010

By JEFF NEWMAN

Staff writer

U.S. House Majority Leader Steny Hoyer said during a telephone town hall Monday night that he believes federal action on a proposed third reactor at the Calvert Cliffs Nuclear Power Plant in Lusby is imminent, a potential harbinger of loan guarantees Constellation Energy has said are imperative to the project’s viability.

The reactor was selected a year ago as one of four eligible for $18.5 billion in U.S. Department of Energy loan guarantees, which serve as insurance for private investors.

In February, about $8 billion in federal loan guarantees was allocated for a new nuclear power plant in Georgia and $2 billion in guarantees were given last week to Areva, a French nuclear-power company and manufacturer of the proposed third reactor, for a uranium enrichment facility in Idaho. The Obama administration is trying to get another $9 billion for the loan guarantee program.

“I think we’re going to see some very positive” movements from the Obama administration in the next few weeks, Hoyer (D-Md., 5th) said, adding that the reactor’s construction, which is expected to create 4,000 jobs, will be very welcome in Southern Maryland. “I’m very supportive of that, and I think we absolutely have to move forward with that.”

The teleconference, the fifth held by Hoyer since 2007, allowed citizens to listen in and also submit questions to the congressman, who encouraged those who didn’t have their inquiries answered to either leave a message afterwards or send his office an e-mail. Hoyer also held a traditional town hall on health care last September.

“Our ongoing dialogue is critical to me and my ongoing representation of this district,” he said.

While the telephone town halls allow thousands to participate compared to the hundreds that may attend at a conventional venue, they have also drawn criticism for limiting personal interaction and allowing calls to be screened.

In opening remarks, Hoyer focused on the economy, particularly job creation and financial reform. Goals include cracking down on the “reckless behavior” of Wall Street banks, cutting long-term deficits, tax credits for companies that hire new workers, preventing foreign outsourcing of jobs, and, in wake of the BP oil spill, investing in clean energy. A proposed reform bill will protect consumers, hold big banks accountable and ensure taxpayers are not on the hook for risky business, making “‘too big to fail’ a thing of the past,” Hoyer said.

Closer to home, the congressman ensured a caller from Brandywine that improvements to the intersection of Route 301 and Route 5, which Hoyer passes through on the way to work, are a priority.

“We waste a lot of gas, a lot of time and a lot of frayed nerves at that intersection,” Hoyer said, adding that the project’s first phase has already begun and its second phase is awaiting funding.

In total, Hoyer fielded 11 calls from his district with topics ranging from prescription medications to immigration reform. While he understands why Arizona recently enacted a new law requiring immigrants to carry proof of legal residency, Hoyer also believes it may be misguided, explaining, “A lot of people worry about big government. A lot of people worry about a national ID card.”

The congressman even took a few moments to talk about football at the University of Maryland, his alma mater, with a caller from New Carrollton.

Hoyer told a concerned caller from Waldorf that there were no plans to cut her social security payments and another from Deale that Congress would consider this week a bill giving substantial assistance to states for Medicaid.

He voiced support for free enterprise, citing China’s movement towards free markets as evidence of communism’s failure and stated that “Investing in the education of our children is the most important investment we can make in the future of America.”

jnewman@somdnews.com



Calvert Cliffs Nuclear Power Plant ( third reactor to be installed unless activists can stop it )
May 21, 2010, 1:30 pm
Filed under: Uncategorized | Tags: , , , , , ,

Get involved in anti-nuke activism http://www.nirs.org

From Wikipedia, the free encyclopedia

Calvert Cliffs Nuclear Power Plant
View of power plant
View of power plant
Data
Country United States
Location Lusby, Maryland
Coordinates 38°25′55″N 76°26′32″W / 38.431892°N 76.442356°W / 38.431892; -76.442356Coordinates: 38°25′55″N 76°26′32″W / 38.431892°N 76.442356°W / 38.431892; -76.442356
Owner Constellation Energy
Operator Constellation Energy
Start of commercial operation Unit 1: 1975
Unit 2: 1977
Reactors
Reactor supplier Combustion Engineering
Reactor type PWR
Reactors active 2
Power
Capacity Unit 1: 873 MW
Unit 2: 863 MW
Total power generation in 2007 Unit 1: 8,104 GW-h
Unit 2: 6,807 GW·h
Average annual generation (last 5 yrs) Unit 1: 7,228 GW-h
Unit 2: 7,003 GW·h
Status Operating
Generators Unit 1: General Electric
Unit 2: Westinghouse
Other details
Architect Bechtel
Constructors Bechtel
License expires Unit 1: 2034
Unit 2: 2036
NRC region Region 1
Website
www.calvertcliffs.com

The Calvert Cliffs Nuclear Power Plant (CCNPP) is a nuclear power plant located on the western shores of the Chesapeake Bay in Lusby, Calvert County, Maryland.

Contents

[hide]

//

Overview

The plant, owned and operated by Constellation Energy, has two 2700 megawatt thermal (MWth) Combustion Engineering Generation II, two loop pressurized water reactors. Each generating plant (CCNPP 1&2) produces approximately 850 megawatt electrical (MWe) net or 900 MWe gross. Each plant’s electrical load consumes approximately 50 MWe. These are saturated steam plants (non-superheated) and are approximately 33% efficient (ratio of 900 MWe gross/2700 MWth core). Only the exhaust of the single High Pressure Main Turbine is slightly superheated by a two stage reheater before delivering the superheated steam in parallel to the three Low Pressure Turbines. Unit 1 uses a General Electric designed main turbine and generator, while Unit 2 uses a Westinghouse designed main turbine and generator.[1] The heat produced by the reactor is returned to the bay, which operates as a cooling heat-sink for the plant.

Unit 1 went into commercial service in 1975 and Unit 2 in 1977.[1] The total cost of the two units was approximately 766 million USD.[citation needed]

Unit 1 had its two steam generators replaced in 2002 and its reactor vessel closure head replaced in 2006, while unit 2 had its two steam generators replaced in 2003, and its vessel closure head replaced in 2007.[citation needed]

The water around the plant (see lower-right-center of photograph) is a very popular place for anglers. Unit 1 & 2 each takes in bay water (from the fenced-in area) to cool its steam driven turbine condensers plus other bay water cooled primary and secondary system heat exchangers. The bay water is pumped out at a nominal flow rate of 1.2 million gallons per minute (75,000 L/s) per unit (Unit 1 and 2) for each steam turbine condenser. The water is returned to the bay no more than 12 °F (6.7 °C) warmer than the bay water. Unlike many other nuclear power plants, Calvert Cliffs did not have to utilize water cooling towers to return the hot water to its original temperature. The warmer water encourages faster growth (relative to the surrounding area) of the small shellfish, plankton, and others at the base of the food chain. These attract the larger fish which are in turn sought after by the anglers. As the water comes out very quickly and creates a sort of artificial rip current, it can be a dangerous place to fish. CCNPP 3 will only need about 10% of the bay cooling water volume needed for Unit 1 and 2 combined. The increase in fish and shellfish impingement and entrainment will be less than 3.5% over Unit 1 and 2 existing conditions.[citation needed]

In February 2009, Calvert Cliffs set a world record for Pressurized Water Reactors (PWRs) by operating 692 days non-stop.[2] (US-EPR), Generation III+[3] In addition, Unit 2’s capacity factor in 2008 was a world-record high of 101.37 percent.[4]

2000 renewal of operating license

In 2000, the Nuclear Regulatory Commission extended the license of the plant for 20 additional years, making Calvert Cliffs the first nuclear plant in the United States to receive such an extension. President George W. Bush visited the plant in June 2005, the first time a president had visited a nuclear power plant in nearly two decades.[5]

Proposal to add a third reactor

UniStar Nuclear Energy announced it will probably build a new advanced US-Evolutionary Power Reactor (US-EPR) at this site. UniStar Nuclear Energy, a Delaware limited liability company, is jointly owned by Constellation Energy (CEG) and Électricité de France (EdF), a builder and supplier of nuclear power plants in Europe. This proposed single nuclear unit will produce approximately twice the energy of each individual existing plant. See Nuclear Power 2010 Program.

On July 13, 2007, UniStar Nuclear Energy filed a partial application to the Nuclear Regulatory Commission to review its plans to build a new nuclear power plant, Calvert Cliffs Nuclear Power Plant 3 (CCNPP 3) based on the AREVA U.S. Evolutionary Power Reactor[6] (US-EPR), Generation III+[3], four loop pressurized water reactor. The remainder of the license application was submitted to the NRC in March 2008. The NRC confirmed its acceptance for technical review in June 2008. The CCNPP 3 reactor will be rated at 4590 MW thermal/1710 MW electrical gross.[citation needed] Plant loads will be approximately 110 Mwe, thus the net generation is 1600 MWe. Plant thermal efficiency will be approximately 36% (ratio of 1710 MWe to 4590 MWth).[citation needed] A final decision by Constellation to start construction is expected by the end of 2009, paving the way for pre-construction activities.

This third reactor will help address the need for more baseload, generating power in the Mid-Atlantic region. The plant will be located south of the existing CCNPP 1&2 and will be set back from the shoreline. Although only a single unit, its power plant footprint will be almost 2 times the size of the twin units CCNPP 1&2. It will have a closed-loop cooling system using a single hybrid mechanical draft cooling tower. It will incorporate plume abatement (no visible water vapor plume). Units 1&2 use an open-cycle heat dissipation system (no cooling towers). Two thirds of the heat produced by the Unit 3 reactor will be released to the atmosphere via the cooling tower. This also is a saturated steam plant with a Main Steam Turbine (one high pressure turbine in tandem with three low pressure turbines) and a Main Generator design similar to Unit 1 & 2. ALSTOM will supply the Main Steam Turbine and Main Generator.

Units 1 and 2 and their support facilities use a well water system for their potable water supply. It consists of five wells that pump water from the second highest aquifer, the Aquia Aquifer, at the minus 400–500 foot below sea level elevation. The State of Maryland limits daily usage for these five wells to 450,000 gallons per day (gpd). Actual daily usage averages 225,000 gpd. Unlike units 1 and 2, Unit 3 will have a desalination plant to produce potable water using reverse osmosis. The desalination plant will produce up to 1,250,000 gallon of potable water per day for Unit 3 and supporting facilities with total dissolved solids (TDS) less than 400 parts per million (ppm). The source for the desalination plant will be the brackish bay water from the makeup supply to the circulating water system. The TDS for the brackish bay water runs 10,000-15,000 ppm. The potable water will be distributed as makeup water for the demineralized water system, miscellaneous potable water services, fire protection and source water for the four ultimate heatsink cooling towers used during normal shutdown and power operation.

On November 13, 2007, UniStar Nuclear Energy filed an application for a certificate of public convenience and necessity with the Maryland Public Service Commission for authority to construct CCNPP 3. This application is being considered in Case Number 9127.[7]

Opponents and supporters of the proposed third reactor at Calvert Cliffs have been involved in a series of public hearings before officials of the U.S. Nuclear Regulatory Commission. In March 2009, Bill Peil of southern Calvert County asked the Nuclear Regulatory Commission to deny an emissions permit for the reactor due to health and safety concerns he maintains the plant poses to the community. UniStar Nuclear Energy President and CEO George Vanderheyden urged the NRC to approve the air permit application.[8]

References

  1. ^ a b “Calvert Cliffs Nuclear Plant”. Constellation Energy. http://www.constellation.com/portal/site/constellation/menuitem.0275303d670d51908d84ff10025166a0/. Retrieved 2010-1-14.
  2. ^ “Calvert Cliffs Nuclear Plant Unit 2 Sets World Record”. Constellation Energy. 2009. http://ir.constellation.com/releasedetail.cfm?ReleaseID=372101. Retrieved 2010-1-14].
  3. ^ a b “EPR: Generation III+ Performance Fact Sheet” (PDF). AREVA NP. 2008-01-04. http://www.areva-np.com/us/liblocal/docs/epr/epr_GenIII_performanceFactSheet090607.pdf. Retrieved 2008-01-09.
  4. ^ “Maryland Chamber of Commerce Visits Calvert Cliffs Nuclear Power Plant”. Business Wire. June 19, 2009. http://www.businesswire.com/news/home/20090619005669/en/Maryland-Chamber-Commerce-Visits-Calvert-Cliffs-Nuclear. Retrieved 2010-04-20.
  5. ^ “Nuclear Technology Milestones”. Nuclear Energy Institute. http://www.nei.org/keyissues/reliableandaffordableenergy/factsheets. Retrieved 2010-01-14.
  6. ^ “EPR: the first generation III+ reactor currently under construction”. AREVA NP. 2008-01-04. http://www.areva-np.com/scripts/info/publigen/content/templates/show.asp?p=1655&l=us&sync=y. Retrieved 2008-01-09.
  7. ^ Case Number: 9127. Maryland Public Service Commission. 2007-11-13. http://webapp.psc.state.md.us/Intranet/CaseNum/CaseForm.cfm. Retrieved 2008-01-06.
  8. ^ NRC hears both sides of nuclear expansion debate

External links